how it all started… a quick start – Part 2

how it all started… a quick start – Part 2

there we were.

an assembly factory in the middle of nowhere – north-western Bavaria, Germany

VxRail servers for the project had been delivered.

Additional Equipment for each customer site was delivered too, Switches, Firewalls, more switches, racks and a truckload of cables.

So we laid the “New Foundation” for the customer in the upcoming year:

– Preparation of a rack in the assembly factory

– shipping of the fully installed rack to the destination site

– (more than once a dissasembly of an rack at the customer site, because preparations were a mess and the rack wouldn’t fit in the elevator)

– installing everything

– powering on the racks

– connecting to the customers existing environment

One Solution Sets for one of the customer sites (work in progress):

assembly factory

Full Rack for one site

VxRail Nodes for a XL-Site

Leave a Reply